Client Alert
COVID-19 Crisis: Force Majeure and Impact on Contracts from an English Law Perspective
Client Alert
COVID-19 Crisis: Force Majeure and Impact on Contracts from an English Law Perspective
March 25, 2020
I. Executive Summary
The COVID-19 virus presents severe challenges to the global economic and commercial market. In the UK, as with many countries around the world, the pandemic has led to the implementation of the biggest curb on public life during peacetime. In addition to the humanitarian impacts of this global crisis, quarantine, travel bans, denial of access and other restrictive measures have severely affected global supply chains and contracting parties’ ability to comply with contractual obligations.
The doctrines of frustration and force majeure as well as the intersection of the two is a complex area of English law. However, in this briefing, we summarize at a high level the key legal issues relating to the invocation of a force majeure clause, as well as some of the issues that General Counsel may face as a consequence of current events.
II. Force Majeure under English Law
The concept of force majeure originated in the French civil law system. Not surprisingly then, in English law, force majeure is neither defined in statute nor in case law.
The concept of force majeure will not be implied into a contract (in contrast to some civil law jurisdictions). It can, however, be invoked, if it is expressly incorporated into the contract.
Whether the force majeure clause is triggered will depend entirely on the words that the parties have used in the contract. It is for this reason that many contracts have force majeure clauses which list out in detail the events which would constitute a force majeure event. Such lists may either be exclusive or non-exclusive. Non-exclusive lists (which tend to be most common) allow for the possibility of other, non-listed events qualifying as force majeure.
Importantly, a party seeking to rely on a force majeure event has the burden of proof and must also establish that its inability to perform the contract was in fact caused by the claimed force majeure event. This requirement of causation is likely to be the key battleground in COVID-19 force majeure cases in the months and years to come, and the focus in any eventual litigation or arbitration will certainly be on whether any travel restrictions, quarantines imposed, lack of available employees or similar specifically impacted the project or party at issue in the period of time surrounding the notice of force majeure.
Some force majeure clauses will expressly state that the party seeking to rely on it was “prevented” from performing due to the force majeure event. If the clause is drafted in this way, the party typically must show that performance of its obligations would have been possible “but for” the COVID-19 outbreak (or the governmental measures taken in response) and that there is no alternative way in which the obligation can be mitigated or discharged. A key issue likely to arise in this context is the nature of governmental measures taken, and whether such measures are mandatory or advisory in nature, together with whether any governmental measure (e.g. the shutdown of a specific plant) was in fact requested by or instigated by the party then claiming force majeure. The English courts have held in the past that a party which has requested a governmental measure cannot then rely upon that governmental measure in a claim for force majeure.
A party relying on a force majeure clause must also show that there are no reasonable steps that it could have taken to mitigate or avoid the effects of the force majeure event.
III. What if There is No Force Majeure Clause in the Contract and/or What About an Alternative to a Force Majeure Claim?
In the absence of an express force majeure clause or as an additional or alternative argument, the defaulting party might attempt to excuse its non-performance by reference to the English doctrine of frustration of contracts.
This doctrine provides that a contract may be discharged on the grounds of frustration when an event or circumstance arises after the formation of a contract that renders its performance physically or commercially impossible or transforms the obligation to perform into a radically different obligation than that to which the party originally agreed.
Although the frustration principle is subject to a very high threshold, it is possible to envisage a range of factual circumstances in which COVID-19 and the ensuing governmental response measures could be construed as a frustrating event.
Another potential alternative is a claim under a change of circumstances or price renegotiation clause, if such a clause is contained in the relevant contract. These clauses are used less frequently in English law-governed contracts, given the general principle under English law that an agreement to agree is not enforceable. That said, if such a clause is included in a contract it will certainly come under close scrutiny by both parties as a result of COVID-19.
IV. Is COVID-19 a Force Majeure Event?
Notwithstanding the severity and the impact of the COVID-19 outbreak, it is not a foregone conclusion that, under English law, a contractual force majeure provision will apply.
If the force majeure clause refers to pandemics and/or epidemics, then it will almost certainly be applicable given that the World Health Organization on 11 March 2020 declared COVID-19 a pandemic. However, the position becomes more uncertain where the clause may, for example, refer to an “act of God” without further definition.
If the outbreak does fall within the scope of the clause, it must then be determined to what extent the contractual obligations are affected. It is possible for example that some obligations within the contract are not impeded by the outbreak and some obligations may simply be postponed. Therefore, both parties will need to closely scrutinize the relevant evidence, including the timing of the alleged performance difficulties as compared to the spread of COVID-19 and corresponding government measures taken in the particular place of operation at a given time.
V. Risk of Getting it Wrong
For the above reasons, careful thought should be applied (and advice taken) before relying on a force majeure clause. If a party declares force majeure but is not contractually entitled to do so, it may expose itself to a claim for repudiatory breach of contract and the other party may be entitled to claim damages as a consequence.
VI. What Steps Should I be Taking Now?
Irrespective of the duration of the crisis, at the time of writing it is safe to say that many major contracts and their obligations will be greatly impaired. It would be advisable to take the following steps:
- Review the wording of force majeure clauses in key contracts, paying particular attention to the list of non-exhaustive events which is often included, and the consequences of triggering a force majeure.
- If a long list of force majeure events is included, it is likely to be helpful (where you are seeking to rely on the clause) if specific wording is included such as “pandemic,” “epidemic,” “outbreak,” “crisis,” or “governmental action.”
- It is important to check the notice provisions of any force majeure clause to check whether a notice is required, when it is required, what information and evidence it must contain and where it should be sent to and by what means.
- Be vigilant for opportunism from counterparties. It is possible that unscrupulous counterparties will seek to use the COVID-19 outbreak as a pretext for seeking to terminate an unfavorable contract on the purported grounds of force majeure. If such a notice is received, obtain the appropriate advice to make sure you are rejecting it effectively and protecting the company’s rights.
- Watch out for wording in new contracts that requires that the event of force majeure is “unforeseeable.” Based on current circumstances, a virus outbreak (or at least the continued effects of the COVID-19 pandemic) would qualify as foreseeable.
- Contact counterparties of contracts which may be affected and discuss a possible renegotiation, or postponement of obligations, as appropriate.
- Consider how the risks associated with this outbreak, or a future outbreak of similar effect, could be provided for and minimized in future contracts.
This briefing was drafted by London Partners Ben Bruton, Daniel Meagher, Michael Stepek, and Matthew Bate. For further information or questions on U.K. law regarding COVID-19 and force majeure clauses, please contact Ben Bruton, Daniel Meagher, Michael Stepek, Matthew Bate, or your Winston relationship attorney.
View all of our COVID-19 perspectives here. Contact a member of our COVID-19 Legal Task Force here.